Quantity
|
Total
|
||
|
|
|||
|
|
|||
Total-Energo LLC performs professional setup of an energy storage system (ESS) based on the Victron Energy Quattro inverter in single-phase configuration. Such a system gives the user full control over consumption, generation, storage and backup power, taking into account tariffs and optimization of energy use from PV.
What does ESS commissioning include
1. Checking equipment compatibility
- Configuration analysis: Quattro → AC Loads / Grid / Generator
- Checking the presence of Cerbo GX or Color Control GX
- Evaluation of connection: VE.Bus, DC cables, CAN (for BMS)
- Presence and correct connection of grid meter (ET112, EM24, EM540, Carlo Gavazzi)
2. Activating ESS mode
- Enabling ESS via Settings → ESS on Cerbo GX
- Selecting the operating mode: Self-consumption only, Optimized, Keep Batteries Charged
- Setting export restrictions: No feed-in or Limited feed-in
3. Charging and discharging parameters
- Setting SOC limits (e.g. 20% – 95%)
- Limiting charge/discharge currents according to the type of battery or BMS
- Activating temperature charge
- Configuring the logic of working with the generator, if present
4. Configuring interaction with PV
- Integration with Victron MPPT controllers or external PV inverters (via AC input)
- Priority distribution: load → battery charge → export
- Generation control, efficiency tracking, autonomous operation during the day
5. Connection to the monitoring system
- Connection to the VRM portal: SOC, PV, import/export, load
- Settings: event logging, email notifications, graphs
- Remote access for the user or support service
6. Testing ESS modes
- Scenario: PV charge → load power → night discharge
- Testing backup power in case of grid failure
- Checking switching between sources: grid → battery → generator
7. Customer briefing
- Training on working with Cerbo GX, VRM
- Recommendations on maintenance, seasonal operation, backup
- Transfer of settings, documentation, technical report
Why is it important to perform commissioning work professionally
- Victron Quattro can work with the network, generator and battery simultaneously — this requires correct switching logic
- Without setup, source conflicts, battery undercharge, overload
- Professional setup ensures efficient, balanced and safe operation
Why choose “Total-Energo” LLC
- Implemented ESS projects on Quattro with a capacity of up to 15 kVA
- We work with batteries: Victron, Pylontech, BYD, SOK, GEL/AGM
- We know the specifics of integrating generators, PV, BMS, monitoring
- Support after setup: VRM, service, updates, diagnostics
- A team of installers and engineers throughout Ukraine